Column & Slab for Fourth Floor Slab 23.05 Mtr in progress
Column & Slab for Fourth Floor Slab 23.05 Mtr in progress
UG & STP Tank work in progress. Current excavation dressing and PCC work front
Sandal Wood trees saved and Wall constructed at Site
South side compound wall excavation & PCC completed. UCR in progress. Saved the Sandal wood tree did the excavation manually and completed the further work
West side compound wall existing feince removed, excavation completed and UCR upto existing ground level completed. Above ground UCR in progress
Projects
Jakson Inns Hotel, Phaltan
Reporting Period
25th March 13 to 1st April 13
Report Date
1st April 13
Report Number
30
North East Corner
South East Corner
South West Corner
North West Corner
Hotel North East View
Hotel View from Highway
Hotel Front View ( North )
Hotel Back View ( South )
Third Floor 16.30 Mtr slab Work casting completed for grid D‐F, 6‐9. above 16.3 Mtr in progress
Third Floor 16.30 Mtr balance slab Work in progress
Projects
Jakson Inns Hotel, Phaltan
Reporting Period
18th March 13 to 25th March 13
Report Date
25th March 13
Report Number
29
North East Corner
South East Corner
South West Corner
North West Corner
Hotel North East View
Hotel View from Highway
Hotel Front View ( North )
Hotel Back View ( South )
Third Floor 16.30 Mtr slab Work casting completed for grid D‐F, 6‐9.